InfrastructureEXPANDApproved
Karnataka approves ₹1,118 crore extra funding for 134-km SH-35 road upgrade
Bengaluru, Karnataka5 Nov 2026
The Karnataka State Cabinet approved an additional ₹1,118 crore to complete a 134-km road project upgrading SH-35 that connects Attibele–Sarjapur–Dommasandra–Gunjur–Varthur–Whitefield–Kempegowda International Airport–Nelamangala. The revised project cost is ₹3,409 crore, up from the initial estimate of ₹2,290 crore, with the increase attributed to implementation changes, higher land acquisition costs, price rises, delays and additional works.
Why it matters
The added allocation enables the stalled/slow road upgrade works—especially the congestion-prone Gunjur–Varthur stretch—to proceed toward completion, affecting connectivity across the Bengaluru periphery and airport approach corridors.
Government of KarnatakaKarnataka Public Works Department