TransportationBUILDUnder Construction

Kochi Metro Pink Line viaduct reported ~70% complete; station works progressing

Kochi, Kerala8 Nov 2026

The Hindu reported that about 70% of the viaduct for Kochi Metro’s 11.20-km Kakkanad extension (Pink Line) is complete, with track-laying expected to begin. It also said 10 of the 11 stations are planned to have entry/exit on both sides of the road; structural work for some station entry/exit structures is reported complete, while land acquisition issues continue to affect parts of Palarivattom Junction and Padamugal stations.

Why it matters

Advancing civil and station works move the Kakkanad metro extension closer to passenger service, improving mass-transit access along this corridor once completed.

Kochi Metro Rail Ltd. (KMRL)