EnergyIMPROVEApproved
India-wide

MNRE extended PLI commissioning timeline for electrolyser plants to Aug 2027

11 Nov 2026

ET Energy reported that the Ministry of New and Renewable Energy agreed to extend the commissioning deadline for several PLI-supported electrolyser manufacturing facilities, allowing commissioning any time up to August 2027 instead of December 2026. The report says companies including Reliance Electrolyser Manufacturing, Adani New Industries, Homi Hydrogen and John Cockerill Greenko Hydrogen Solutions are deferring commissioning due to weak green hydrogen demand while retaining PLI eligibility under the extended timeline.

Why it matters

The extension keeps PLI eligibility intact while allowing manufacturers to delay the start of their incentive period until orders materialise, reducing the risk of running plants without sufficient demand.

Ministry of New and Renewable Energy (MNRE)