InfrastructureIMPROVEUnder Construction

GCC reports 493.83 km of Chennai stormwater drains desilted as of Aug 28, 2026

Chennai, Tamil Nadu28 Aug 2026

The Greater Chennai Corporation said it had completed desilting 493.83 km (29.42%) of the 1,671.6-km stormwater drain network taken up through contracts as of August 28, 2026. It reported work under way along 77.29 km (4.62%), with 1,109.2 km (65.94%) yet to be taken up; it also said 2,351 roads and 43,614 machine holes were completed as part of the work.

Why it matters

Desilting stormwater drains and related catch-pit cleaning can improve drainage capacity ahead of the monsoon, reducing waterlogging risk on city roads.

Greater Chennai Corporation (GCC)