Bhandai–Keetham 26.5-km bypass rail line in Agra is under construction; 82% civil work done

Agra, Uttar Pradesh7 Sept 2026

Construction is underway on the 26.5-km Bhandai–Keetham bypass rail line in Agra division as part of the Mathura–Jhansi third-line project (estimated cost ₹5,960.7 crore). Railway officials said the bypass is expected to be completed by 2026-12-31; railway data cited in the report says about 82% of civil work is complete, with 53 of 57 minor bridges completed and superstructure finished on 13 of 18 major bridges.

Why it matters

If completed and brought into service, the bypass would provide an additional route around Agra, easing congestion and improving passenger and freight train movement on the Delhi–Mumbai corridor section.

Indian RailwaysNorth Central Railway (Agra Division)